Can Free Float Be Greater Than Total Float
Primavera Did It Again. How Can That Free Float Is Higher Than Total Float (For Activities with Total Float >=0). It Is Sufficient That, Inside the Schedule...
Primavera did it again. How can that Free Float is Higher than Total Float (for activities with Total Float >=0). It is sufficient that, inside the schedule, you have some activities with negative Total Float.
Is total float greater than free float?
Primavera did it again. How can that Free Float is Higher than Total Float (for activities with Total Float >=0). It is sufficient that, inside the schedule, you have some activities with negative Total Float.
What if free float is negative?
Negative float, also known as negative slack, is the amount of time beyond a project’s scheduled completion that a task within the project requires. … Essentially, negative float is the amount of time that must be saved to bring the project to completion on time.