How to Sync the Perforce Client to a Particular Change List Using P4 Sync Command
Let Us Assume Depot Contains Change Lists: Change Lists: 300 299 280 270 260 I Would Like to Sync My Client at Change List 280. If I Do P4 Sync: My Client Will...
let us assume depot contains change lists :
change lists : 300 299 280 270 260
I would like to sync my client at change list 280.
if i do p4 sync : my client will be updated with cl : 300 (latest one) which i'm not looking for.
How can we achieve this ?
2 Answers
Perforce uses "@" to indicate change number, so
p4 sync @280
p4 sync ...@280
Accepted answer didn't work for me
To check latest synced CL: p4 changes -m1 //...#have